Case study · 2026
Case study: NORSOK Super-Duplex Chemical Injection Skids | Riis Energy Services
Fabrication of four 25Cr super-duplex chemical injection skids to NORSOK standards for an offshore platform.
- Tananger, Norway
- EPC contractor
- 7 months
- ASME & NORSOK Fabrication and Machining
The challenge
Tight ferrite and hardness requirements for 25Cr super-duplex piping, and a weight limit per skid for offshore lifting.
Our solution
Welding procedures qualified to NORSOK M-601 with 100% ferrite measurement, PMI on all components and laser-tracker dimensional control.
The results
Weld repair rate of 0.8% and all skids within 1.5% of target weight.
Timeline
- Month 1 WPQR and material receipt
- Months 2–6 Fabrication & NDT
- Month 7 FAT and load-out