Plant-wide corrosion under insulation screening of 38 km of insulated piping, delivered during operation without a shutdown.
- Abu Dhabi, UAE
- NOC gas processing
- 14 weeks
- Intégrité des pipelines et inspection CUI
Le défi
The operator had 38 km of insulated carbon-steel piping operating between 60 °C and 175 °C, with two CUI leaks in 18 months and no reliable data on where the next one would occur. Removing insulation everywhere would have cost more than the annual maintenance budget.
Notre solution
Northline ran a risk-based screening: PEC on 100% of accessible lines, profile RT at supports and dead legs, and PAUT follow-up at 1,240 flagged locations. Results fed a remaining-life model and a prioritised repair list.
Les résultats
Insulation removal was limited to 6% of the piping. 17 locations below minimum required thickness were repaired before failure. No CUI leaks in the 12 months after completion.
Chronologie
-
Week 1
Mobilisation & risk ranking
Crew mobilised, P&IDs reviewed, 38 km ranked by CUI susceptibility.
-
Weeks 2–8
PEC and profile RT screening
Full screening of accessible lines, 1,240 locations flagged.
-
Weeks 9–12
PAUT follow-up
Quantitative wall-thickness mapping at flagged locations.
-
Weeks 13–14
Remaining-life model & repair plan
Prioritised repair list delivered, 17 critical items fixed.