Referanseprosjekt · 2024

Case study: 15,000 psi HPHT Wellhead Package, North Sea | Riis Energy Services

Design, manufacture and testing of 6 compact wellheads and 15,000 psi Christmas trees to PSL 3G, material class HH-NL.

Packages delivered
6
Rated pressure
15,000 psi
FAT non-conformances
0
Delivery vs plan
3 weeks early

Utfordringen

An infill drilling campaign required 15,000 psi, 150 °C sour-service equipment on a compressed schedule to match rig availability.

Vår løsning

We adapted our qualified CW-13 compact wellhead, ran PR2 validation for the new tree block, and set up a dedicated test-cell shift pattern to test two assemblies per week.

Resultatene

All 6 packages delivered 3 weeks ahead of rig arrival with zero non-conformances at client FAT.

Tidslinje

  1. Month 1 Design review & PR2 plan
  2. Months 2–7 Forging, machining, assembly
  3. Months 8–10 Hydro and gas testing, FAT
  4. Month 11 Delivery to supply base