Referanseprosjekt · 2025

Case study: 4,800-joint Refinery Turnaround with Controlled Bolting | Riis Energy Services

Flange management and controlled bolting of 4,800 joints during a planned refinery turnaround.

Joints made up
4,800
Start-up leaks
2 (was 41)
Crew at peak
64
Recordable injuries
0

Utfordringen

The turnaround window was fixed at 32 days and the previous event had 41 leaks at start-up.

Vår løsning

Northline deployed a 64-person bolting crew with a digital joint register, tagged every joint, and applied ASME PCC-1 assembly procedures with independent QC sign-off.

Resultatene

Start-up with 2 minor leaks (down from 41) and turnaround completed one day early.

Tidslinje

  1. T-8 weeks Joint register & procedures
  2. Days 1–28 Break-out and make-up
  3. Day 31 Leak test and start-up

Planlegger du et lignende prosjekt?

Be om tilbud